|
| |
|
The
project Engineering Department (PED)
was established in 1985 to:
|
- provide
System engineering and optimisation
- engineer
and procure the balance of plant systems
|
|
for
gas turbine and steam turbine based power plants on turn-key
basis. Subsequently, it has been geared up to provide engineering
and technical support for various turnkey projects of any scale
and magnitude in India and abroad. PED has engineered several
gas turbines and steam turbine based power projects on turn-key
basis till date. The list of customer references is enclosed.
|
|
The
erection and commissioning of the entire power plant, namely
power block equipment (GT, HRSG, ST and Boiler) and balance
of plant equipment, are carried out by respective power sector
groups of BHEL, namely Northern Region (PSNR), Eastern Region(PSER),
Southern Region(PSSR) and Western Region(PSWR). Depending upon
the location of site, one of these four agencies carryout the
complete erection and commissioning of power plant. |
|
| Steam
turbine based systems: |
|
This
system consists of a boiler, steam turbine generator and balance
of plant systems. PED takes up steam turbine based plants upto
60Mw capacity . |
|
| Gas
Turbine based systems : |
| These
are classified into three catagories: |
|
- Simple
cycle power plants,
- Co-generation
plants and
- Combined
Cycle power plants
|
|
Simple
cycle power plant consists of only gas turbine generator and
its auxiliary systems. The exhaust gas from GTG is let into
atmosphere. |
|
Co-generation
plant consists of gas turbine /gas turbine generator with HRSG
to generate steam using exhaust gases from GT. Steam generated
is used either to generate power or in process. |
|
| The
steam turbine plants of more than 60Mw capacity taken up by
Project Engineering Management group based at New Delhi. This
division also engineers and executes thermal power plants. |
|
Combined
Cycle power plant consists of gas turbine generator, HRSG and
steam turbine generator. The steam generated from HRSG is fed
to steam turbine for power generation. |
|
These
gas turbine and steam turbine plants require various auxiliary
systems to support gas turbine, heat recovery steam generator,
steam turbine and boiler for reliable and continuous operation
of plant. These are also called balance of plant systems. The
balance of plant systems and works are classified into four
types namely Civil, Mechanical, Electrical and Controls & Instrumentation. |
|
PED
carries out the system design and equipment selection for combined
cycle and co-generation plants. This includes selection of Gas
Turbine model, HRSG parameters, Steam turbine capacities, Integration
of power block equipment and sizing of balance of plant systems.
PED also carries out optimization studies of thermal systems. |
|
The
department has forty engineers to take of Civil, Mechanical,
Electrical and C&I systems and works. PED is an engineering
group which procurement of balance of plant equipment and systems.
The type of works and systems taken up by the department are
elaborated below : |
|
| Civil
discipline activities: |
|
The
civil engineering group will carryout the design and estimation
of the following works. |
|
- Site
leveling and grading
-
Soil investigation
- Green
belt development
- Roads
within power plant area
- Foundation
design for all equipments
- Power
plant buildings like Gas turbine hall, Steam turbine building,
control room buildings / enclosures for balance of plant
equipment / machinery.
- Non-plant
buildings like administration building, canteen, vehicle
parking lots, guardrooms and rest rooms.
- Storm
water drains and trenches within power plant area.
-
Pipe racks and pipe sleepers and pipe troughs.
-
Water reservoirs for power plants.
|
|
The
analysis and design are carried out using advanced software
packages like STAAD-Pro, Ex-Steel. |
|
| Mechanical
discipline activities: |
|
The
mechanical engineering group carries out the following work
content. |
|
- Thermal
system engineering, optimisation and integration.
- Power
plant guarantees, heat balance diagrams and water balance
diagrams.
- Power
plant engineering
- Balance
of plant systems engineering and procurement
|
- Gas
fuel conditioning systems
- Liquid
fuel storage and conditioning systems
- Water
treatment systems (Raw water, DM water, service and potable
water systems)
- Effluent
treatment and disposal systems
- Nitrogen
and compressed air systems
- Cooling
water systems for condenser
- Auxiliary
cooling water systems
- Material
handling systems
- Fire
protection and fire alarm systems
- Chemical
dosing systems
- Air
conditioning and ventilation systems
- Black
start and emergency shutdown systems
- Steam
and feed water systems
- Coal
and ash handling systems
|
- Power
plant piping for fuels, steam, feed water, nitrogen, compressed
air, effluent disposal etc.
- Workshop
equipment
- Performance
guarantee tests.
|
|
| Electricals
discipline activities: |
|
| 1.
Scope of Power plant jobs include total turnkey power stations
set up to |
|
a)
directly feed inhouse customer requirements with or without
local grid support (captive power plants)
b) evacuate bulk power at terminal point
(utility stations) |
|
| 2.
Thus, following system engineering activities (engineering,
procurement & commissioning assistance) are conducted |
|
a)
Electrical system studies to finalise the sizes of sources (generators,
stepup & distribution transformers, fault limiting transformers/reactors),
generating and evacuation voltages, prospective fault currents
and terminal voltages at various voltage levels.
b) Overall key single line diagram (SLD)
and SLDs of individual sub system & package
c) Protection co ordination and relay
settings
d) Stepup, distribution & fault limiting
transformers, reactors
e) Switchboards for each voltage level
f) Reliable sources (DG sets, UPS, DC
systems)
g) Control and synchronizing philosophy
h) Energy Management of total asset
of customer (power plant plus process industry) including centralized
control and monitoring, optimal load sharing of various sources,
export/import regulation with respect to local grid, load shedding
to ensure reliable uninterrupted supply to critical loads to
the process industry, advice on power factor improvement and
starting of large motors, . . .
i) Black start and normal/emergency
shutdown requirements
j) SCADA for Remote control of power
station
k) Plant Illumunation
l) Plant intercommunication
m) Cables and cable trays and accessories
n) Earthing devices (NGT, NGR, solid,
electronic earthing) and underground & above ground earthing
o) Layouts of switchgear rooms, transformer
yards, cable routes, . . .
p) Cable schedules and interconnection
charts |
|
| Instrumentation
discipline activities: |
|
| 2.
Following system engineering activities (engineering, procurement
& commissioning assistance) are conducted |
|
a)
Balance of plant control system, generally implemented through
DCS and PLCs
b) Integration of total plant controls
- Gas turbine, steam turbine, generators, compressors, mechanical
packages, balance of plant, . . . through DCS
c) Control & safety valves
d. Pressure reduction & Desuperheating
systems
e) Flow elements
f) Other Field instruments
g) Control loops and logics
h) Layouts and instrument hookups
i) Cable schedules and interconnection
charts |
|
| B.
Facilities and infrastructure: |
|
1)
The department is equipped with the latest state of art facilities
& software packages for system studies, illumination and earthing
sizing, etc
2) Stringent specifications
of leading domestic and overseas consultants (EIL, DCL, MECON,
Electrowatt, . . . ) and customers (NTPC, IOC, BPCL, HPCL, PDO,
Oman, Ministry of Elec & Water, Oman, TNB, Malaysia, . . . )
have been complied.
3) Continuous upgradation
of technical knowhow about system engineering aspects as well
as products takes place by frequent participation in witness
of type tests, interaction with leading consultants, customers
and third party houses. |
|
| SPECILIZED
SOFTWARE USED IN PED |
| MECHANICAL |
|
|
Sl.no
|
Name
of the Software
|
Description
|
|
1
|
PDMS
|
3D
modelling of plant design. Used for generation of plant
layouts, isometrics, BOQ other related 2D drawings
|
|
2
|
PDS
|
3D
modelling of plant design. Used for generation of plant
layouts, isometrics, BOQ other related 2D drawings
|
|
3
|
GTPRO
|
A
total used for system selection , Heat balance diagrams
for gas turbine based cogen & combined cycle plants,
hardware design to achieve given thermodynamic input
used for economic analysis & feasibility studies.
|
|
4
|
GT
MASTER
|
Provides
accurate predictive off design simulation of HRSG, steam
turbine, condenser cooling towers of GT based cogen
& combined cycle plants. Takes input from GTPRO
|
|
5
|
PEACE
|
Software
tool used for plant engineering estimates, electrical
load list, civil & construction estimator for proposal
engg. of inputs for estimation hours.
|
|
6
|
AUTOPIE+
|
Pipe
stress analysis program
|
|
7
|
PLANTFLOW+
|
Used
for flow analysis & pipe sizing
|
|
8
|
NATASHA
|
Process
dynamic flow analysis pipe sizing for hydrocarbon processing
plants
|
|
9
|
GOW
|
Used
for thermodynamic properties of gas, oil, water steam
|
|
10
|
IPS
|
Used
for estimation of pipes, fittings, valves BOQ for bulk
procurement provides link for online purchase requisitions
and despatch instructions for piping
|
|
11
|
IPGS,IMIS
|
For
online material indenting & partlist generation
|
|
12
|
CAE
PIPE
|
Used
for piping stress analysis software link to PDMS
|
|
|
| ELECTRICAL |
|
Sl.no
|
Name
of the software
|
Description
of the software
|
|
1
|
CYME
|
Used
for electrical system studies
|
|
2
|
HT
Gear, LT Gear
|
Software
tool for preparation of SLDS, specifications for HT
switch gear & LT switchgear
|
|
|
| CIVIL |
|
Sl.no
|
Name
of the software
|
Description
of the software
|
|
1
|
STAAD-3
|
Used
for Analysis & civil foundation design
|
|
2
|
X
STEEL
|
Software
tool generation of structural steel assembly drawings
& part drawings. Software link to PDS
|
|
|
| |
| |